Request a quoteFive levels take a facility from equipment in a factory to systems proven under failure. Here is what each level proves, the evidence it produces and who signs it off.
Level 1 happens before anything ships. Switchboards, RPPs, manifolds and skids are tested in the factory against a script agreed in advance, and you can witness the test in person or remotely.
A fault found here is fixed on the bench, not on a live site.
Each unit is inspected on arrival against the approved submittals, stored and protected until it is installed, then checked against the drawings once it is in place.
Electrical systems receive their dead tests before they are energised: continuity, insulation resistance, polarity, phase rotation and protective device settings.
Liquid systems are pressure tested, flushed with the CDUs isolated and filled, and the fluid is tested in a laboratory.
Every system is run through its operating modes, alarms and failovers on its own, under load. Load banks and heat load emulators stand in for IT that is not yet installed.
All systems run together while real failure scenarios are applied: loss of utility, generator start and transfer, UPS transfer and retransfer, loss of cooling and fire alarm cause and effect.
The commissioning manager or commissioning authority on your project signs off each level. Contractors and suppliers provide the scripts, the records and the people who witness and run the tests for the levels in their scope.
Where your project has its own commissioning matrix, the levels and their evidence follow it.