Request a quoteA practical checklist for clients and consultants attending a factory acceptance test, so problems are found in the factory and not on site.
Factory acceptance testing (L1) is the cheapest place to find a problem. Once equipment is on site, every fix costs access, time and programme. If you attend a witnessed FAT, this is what to look at.
Agree the test procedure in advance: what will be tested, how, and what counts as a pass. Ask for the drawings the test will be checked against.
Check the build against the approved drawings: component ratings, cable sizes, labels and the general arrangement. Labels should match the drawings exactly.
Insulation resistance, continuity, functional checks of protection and interlocks, and the operation of control and monitoring. Ask to see the results recorded as the tests run, not afterwards.
For liquid cooling manifolds and pipework: pressure testing, leak checks and the cleanliness of the internals.
You should leave with signed test records, a list of any open points and an agreed plan to close them before shipping.
Open points are closed and evidenced before the equipment leaves. The FAT records then become the first part of the commissioning file that continues through L2 to L5. See our guide to commissioning levels L1 to L5.
Send us your drawings or describe the problem. We contact you within one working day.